| CLIENT
|
|
Wavespec
Ltd, Maldon, Essex, UK
|
| |
| LOCATION
|
|
Sembawang
Shipyard, Singapore and Swan Hunter Shipyard, Wallsend
|
| |
| PERIOD
|
|
January
1995 To December 1995 and January 1996 To February 1998
|
| |
| PRO-TEC |
|
Was
here with an Electrical Projects Engineer.
|
| |
| PROJECT
|
|
To
assist in the design and development of an electrical power
system associated with the conversions of a bulk carrier to
a pipelay vessel. To scrutinise and approve of the design
of subcontractors machinery and equipment and supervise the
installation of same. Prepare commissioning procedures for
all systems and oversee proper completion of same. All on
behalf of Allseas Engineering of the Netherlands.
|
|
|
Bulker
to pipelayer-metamorphosis
|
 |
|